Overview

Overview
The CID is working to be a catalyst for positive change in North Fulton. Watch the video...

Windward/Marconi Intersection Improvement

Completion Date: April 1, 2014

Total CID Investment: $150,000.00

Partner: City of Alpharetta

The North Fulton CID and the City of Alpharetta have partnered to improve the operational efficiency of Marconi Drive and its intersection with Windward Parkway. The improvements included widening Marconi Drive to extend the two northbound through lanes to the Windward Parkway intersection. 

The City of Alpharetta performed the design of the improvements in house. The North Fulton CID provided the $150,000 funding for and oversaw the construction. The project was awarded to contractor E.R. Snell and construction is completed. The project was completed and open to traffic on April 1, 2014.